Rendering Project, Patcham

Rendering Project, Patcham

Stage 1:

• Preparation of wall area and walls ready for rendering
• Install a surface protection system to drive and surrounding the building, made up of a D.P.M. and 1200 x 2400 boards
• The loose render in areas, agreed on site visit, to be removed
• All remaining surface areas to have a bonding agent, S.B.R. applied
• Waste to be removed from site and disposed of

Labour : Duration of works expected to be up to 5 days for a small team of operatives.

Materials : D.P.M., 1200 x 2400 sterling board x 15 sheets, tarpaulins, waste removal and sundries.

Stage 2:

• Rendering the entire house at ground level
• Fit new window beads and apply a scratch coat followed by a top coat
• A flexi render mesh to be fitted during the scratch coat stage, both coats to have water-proofing additives included.

• Materials such as two types of sharp sand and cement to be delivered on a prepared/protected loading and mixing area (requires full use of the driveway during these works.)

Labour : Duration of works to be up to 10 days for a small team of operatives.

Materials : sharp sand, plastering sand, cement, S.B.R, motor additives, flexi mesh, edge and corner beads mobile scaffolding

See some of our other completed projects

Comments for this post are closed.